When the Enable Automatic Date Propagation toggle on the Production Order Linking Setup page is turned on, date/time changes in linked production orders propagate automatically. The system displays a preview dialog before applying changes.
Date propagation
Date propagation synchronizes schedules between upstream and downstream production orders:
- Forward propagation: Upstream finish date/time drives downstream start date/time.
- Reverse propagation: Downstream start date/time adjusts upstream finish date/time.
- Routing offsets: The system uses BC routing offsets (Wait Time, Safety Lead Time) to calculate dependent dates.
- Lock handling: Locked downstream orders block date moves with clear error messages and resolution options.
When you change a date/time on a linked production order, the system displays the Date Propagation Preview page automatically.
You can view/enter the required information in the following fields:
| Field | Description |
|---|---|
| Production Order No. | Specifies the production order affected by date propagation. |
| Line No. | Specifies the production order line number. |
| Item No. | Specifies the item number. |
| Description | Specifies the item description. |
| Current Starting Date-Time | Specifies the current starting date and time. |
| New Starting Date-Time | Specifies the proposed new starting date and time. |
| Current Ending Date-Time | Specifies the current ending date and time. |
| New Ending Date-Time | Specifies the proposed new ending date and time. |
| Date Change (Days) | Specifies the number of days the schedule will shift. |
| Routing Offset Applied | Specifies the routing offset used for calculation (Wait Time, Safety Lead Time). |
| Lock Status | Specifies the lock status (Unlocked, Locked, Partially Locked). |
| Conflict | Specifies any conflicts preventing date propagation. |
On the action bar, you can select Accept to apply the changes or Cancel to revert.