What's new in version 2602.1.0.0
Enhancements/Modifications
With this release of the Aptean Production Over Pick extension, the expected component quantity used to check sufficient input consumption when finishing a production order is calculated in proportion to the actual Finished Qty. field value of the production order line. Previously, the check compared the actual consumption against the full planned expected quantity regardless of how much output was actually finished, which caused the error "Input is not complete for all items. The order cannot be finished." even when the recorded consumption was proportional to a partially finished output. As a result, a production order can now be finished for a partial quantity when the recorded input consumption is proportional to that quantity, within the configured Allowed % Under-pick field value tolerance.